Completed

Construction of 53.80 Km main and 3.9 Km loop lines under ” Construction of a New Railway Line from Majhgram to Dhalarchar via Pabna”

Project Overview

Construction of 53.80 Km main and 3.9 Km loop lines under ” Construction of a New Railway Line from Majhgram to Dhalarchar via Pabna”

Construction of 53.80 Km main and 3.9 Km loop lines including construction of Level crossing gates and other structures, curve posts etc. construction of Embankment with supplying of all requisite materials and manpower for new track from KM 25+000 to KM 78+800 in between Pabna to Dhalarchar under ” Construction of a New Railway Line from Majhgram to Dhalarchar via Pabna”

project details

  • Year of Completion:

    20/06/2019
  • Employer:

    Bangladesh Railway
  • Location:

    Majhgram to Dhalarchar via Pabna
  • Contact Value:

    BDT. 5,592.59 Million, US$. 70.84 Million

Related projects

Project Construction of Broad Gauge Rail line from Madhukhali to Magura via Kamarkhali. Major Bridge-1 : 549m with 1683m Viaduct, Major Bridge-2 : 90m & Underpass 60m

Contact Value:   BDT. 4489.49 Million

Construction of four lane asphalt carpeting road with road divider, drain, culverts & footpath from Talaimary mour to Katakhali. (Contract No. RCC/EGP/01/2021-22, E-Tender ID No. 554463). “

Contact Value:   BDT 934.86 Million

Cox’s Bazar Airport (Phase-I)

Contact Value:   US$ 5.30 million

Radisson Water Garden Hotel #5
Railway Line from Majhgram to Dhalarchar via Pabna

Contact Value:   US$. 69.90 million

Reinforced Concrete Works Package – 4 of HSIA Expansion Project, Dhaka